Putnam Resource Allocation Model

The Lawrence Putnam model describes the time and effort requires finishing a software project of a specified size. Putnam makes a use of a so-called The Norden/Rayleigh Curve to estimate project effort, schedule & defect rate as shown in fig:

Putnam Resource Allocation Model

Putnam noticed that software staffing profiles followed the well known Rayleigh distribution. Putnam used his observation about productivity levels to derive the software equation:

Putnam Resource Allocation Model

The various terms of this expression are as follows:

K is the total effort expended (in PM) in product development, and L is the product estimate in KLOC .

td correlate to the time of system and integration testing. Therefore, td can be relatively considered as the time required for developing the product.

Ck Is the state of technology constant and reflects requirements that impede the development of the program.

Typical values of Ck = 2 for poor development environment

Ck= 8 for good software development environment

Ck = 11 for an excellent environment (in addition to following software engineering principles, automated tools and techniques are used).

The exact value of Ck for a specific task can be computed from the historical data of the organization developing it.

Putnam proposed that optimal staff develop on a project should follow the Rayleigh curve. Only a small number of engineers are required at the beginning of a plan to carry out planning and specification tasks. As the project progresses and more detailed work are necessary, the number of engineers reaches a peak. After implementation and unit testing, the number of project staff falls.

Effect of a Schedule change on Cost

Putnam derived the following expression:

Putnam Resource Allocation Model

Where, K is the total effort expended (in PM) in the product development

L is the product size in KLOC

td corresponds to the time of system and integration testing

Ck Is the state of technology constant and reflects constraints that impede the progress of the program

Now by using the above expression, it is obtained that,

Putnam Resource Allocation Model

For the same product size, C =L3 / Ck3 is a constant.

Putnam Resource Allocation Model

(As project development effort is equally proportional to project development cost)

From the above expression, it can be easily observed that when the schedule of a project is compressed, the required development effort as well as project development cost increases in proportion to the fourth power of the degree of compression. It means that a relatively small compression in delivery schedule can result in a substantial penalty of human effort as well as development cost.

For example, if the estimated development time is 1 year, then to develop the product in 6 months, the total effort required to develop the product (and hence the project cost) increases 16 times.